FEBRUARY 2025 UPDATES
February 28, 2025 Dan's Carpet Flooring expedited the installation of the flooring and our flooring is 100% complete! MBC removed the existing exterior door disposing of all debris. Re-framing is in process so the fire proof door installation. Bright Electric completed wiring for the HVAC exterior unit installing switches and outlets for service, as planned. February 24, 2025 As of Friday, February 24, the HVAC system is installed and has been tested. Brackets to secure our audio visual equipment are now onsite to be installed. MBC opened the wall to install wood paneling where the tv will be mounted. February 9, 2025 On Wednesday, 2/5, the building inspector did a walk-through to look at the dropped ceiling. We passed! Also last week, Interstate Fire & Safety passed the final inspection for the flow of water in the sprinkler's line. Interior painting has been happening. February 2, 2025 Last week, Bright Electric completed the connection of electric wiring for outlets, switches, and lighting and the installation of all smoke detectors and strobe lights. The "rough" fire inspection passed with no issues. Polytemp finished installing the PVC drain pipes. All condensing lines for interior units have been installed. Murphy Brothers completed the first coat of paint in the sanctuary and multi-purpose room, as all areas had been closed, taped and primed in preparation. The pocket door from the pantry to the MPR has been installed. They continued with the installation of the acoustic ceiling tile in the sanctuary. On Thursday, Paul Gross, Kevin Weber and Ken Perry delivered our pulpit to the new space. On Friday morning, Paul and our tech consultant Kris met with Bright Electric onsite to review the location of the wiring needs for our audio visual equipment. |
|
2024 Updates
As of 12/22/2024 The space at 210 North Central Ave is rapidly taking shape. Our contractors, Murphy Brothers, have inspections scheduled for the "rough" work on plumbing, electrical, framing, and HVAC. The space will be ready for walls, insulation, ceiling, and flooring. Fabricating the cabinets for the pantry and for the doors will take us into early to mid February as the target for occupancy. As of 11/21/2024 We received the building permit from the Town of Greenburgh on Friday, November 15. Demolition work started on Monday, November 18. Multiple contractors are engaged in the work. Members of the board will monitor construction as we move forward. |